No Milestone Means of verification WP Lead Month
MS1 Basic design Design basis ready for design appraisal WP3 WS 8 Sept 2016
MS2 Design appraisal Feedback from third party assessment regarding the basic design WP5 DNV-GL 10 Nov 2016
MS3 Construction tender Public tender for selection of subcontractor for construction WP3 WS 10 Nov 2016
MS4 Detailed design Detailed design ready for design review WP3 WS 15 April 2017
MS5 Design approval Feedback from third party assessment and design approval WP5 DNV-GL 17 June 2017
MS6 Construction Start construction of WEC and PTO WP3 WS 19 Aug 2017
MS7 Installation tender Public tender for selection of subcontractor for installation WP3 WS 24 Jan 2018
MS8 Start installation Start installation of WEC WP4 JDN 30 July 2018
MS9 Commissioning Start production of electricity to the grid WP4 PARK 42 July 2019
MS10 Transfer of the WEC to PARK Transfer of the WEC to PARK for continued energy production WP6 WS 60 Jan 2021